Spring Grove

Spring Grove Dam is a new mass concrete dam in the KZN midlands on the Mooi River close to Rosetta...

The main contractor, Group 5, approached JWE to be part of the team to build this elegant dam. JWE was a formwork and finishing sub-contractor to Group5 during this construction period which ran as a continuous concrete pour 24hrs a day 7 days a week. The formwork on the main wall was lifted on average twice a day but up to 4 times a day towards the top of the wall. Concrete was supplied to the wall in ADTs, spread by bulldozer and compacted by ride on rollers. Total on site duration was 4 months.