Dairy Day Processing Plant

The new Dairy Day facility has recently opened and commenced production...

Dairy Day is a new milk processing facility in Howick, KZN designed to handle 600,000lt of milk per day at maximum production. JWE was first approached by the shareholders of Dairy Day in July 2014 to construct the facility, which still required designs. JWE moved onto site 3 months later in a cost-plus type contract which enables the design team, brought on board and co-ordinated by JWE, to design-on-the-fly. The facility is a 12,000m2 factory comprising receiving areas, processing areas, packaging areas, cold rooms, dispatch areas, a powder plant and wastewater treatment plants. Total construction period was 17 months.